The hot tub is in place and wired up, I can put water in it as son as they finish the ceiling over it, which might be next week.
The office and south bedroom upstairs have drywall and plaster, waiting on the last coat of mud and sanding. The flooring is here and the trim for those rooms is in the pre-painting stage. Wall paint is picked out and here for both rooms. Maybe 3 -4 weeks on both of those.
The basement has lights and a functional 1/2 bath. When it's done being used as a paint/prep area then it will get the drywall or equivalent that it needs. No rush on that.
Heat is done to all of the rooms that it can be for now, which is everything but the front entryway.
On the first floor, we're still waiting (now they say March 4th) for the flooring for the new bathroom/laundry room. laundry, sink and shower are all functional. Toilet, Door and baseboard trim await flooring.
Also on the first floor, the pink powder room is gone and the new bedroom is framed and has wiring. The new entry is mostly framed and wired. Flooring is picked out and here for both rooms, but it'll be a while yet before they're ready for it.
Things not yet started - demoing the east end basement stairs to make room for the first floor bedroom closet and the dumbwaiter which will come up into what is currently a mop/cleaning closet next to the kitchen. The reason for the dumbwaiter is that the basement is slated for firewood storage, both for the (not yet even selected) wood boiler and the wood stoves on the first floor. It's an easy way to get the wood upstairs and we have the space for it.
The office and south bedroom upstairs have drywall and plaster, waiting on the last coat of mud and sanding. The flooring is here and the trim for those rooms is in the pre-painting stage. Wall paint is picked out and here for both rooms. Maybe 3 -4 weeks on both of those.
The basement has lights and a functional 1/2 bath. When it's done being used as a paint/prep area then it will get the drywall or equivalent that it needs. No rush on that.
Heat is done to all of the rooms that it can be for now, which is everything but the front entryway.
On the first floor, we're still waiting (now they say March 4th) for the flooring for the new bathroom/laundry room. laundry, sink and shower are all functional. Toilet, Door and baseboard trim await flooring.
Also on the first floor, the pink powder room is gone and the new bedroom is framed and has wiring. The new entry is mostly framed and wired. Flooring is picked out and here for both rooms, but it'll be a while yet before they're ready for it.
Things not yet started - demoing the east end basement stairs to make room for the first floor bedroom closet and the dumbwaiter which will come up into what is currently a mop/cleaning closet next to the kitchen. The reason for the dumbwaiter is that the basement is slated for firewood storage, both for the (not yet even selected) wood boiler and the wood stoves on the first floor. It's an easy way to get the wood upstairs and we have the space for it.